1. OBJECTIVE
The objective of this document is to present a summary of costs in support of the Environmental Impact Statement (EIS). This report provides a rough estimate of the costs for disposal of 70,000 metric tons heavy metal (MTHM) in the potential repository as well as incremental waste amounts for each of three thermal loading cases described in the EIS. In addition, summary costs for waste transportation, integration, and institutional program elements are presented. It should be noted that this report is primarily based on and supported by project cost estimates from the Viability Assessment of a Repository at Yucca Mountain (DOE 1998a), and the Analysis of the Total System Life Cycle Cost of the Civilian Radioactive Waste Management Program (DOE 1998b), as well as EIS engineering files for the repository surface, subsurface, and waste package elements.2. SCOPE
2.1 REPOSITORY ELEMENTS OF COST AND BASIS
2.1.1 Elements of Cost
The following areas are the major categories that make up the repository. These areas were also presented in the Viability Assessment (VA) and the Total System Life Cycle Cost (TSLCC) which was used as the primary basis of the cost estimates for the EIS:2.1.2 Basis of Estimate
Based upon the VA and the Expanded Environmental Impact Statement Feasibility Assessment (CRWMS M&O 1997), the EIS has specified thermal loading cases implementing alternatives for three alternative areal mass loadings (AMLs): "high," "intermediate," and "low" be addressed. These cases can be described as follows:2.2 NON-REPOSITORY ELEMENTS OF COST AND BASIS OF ESTIMATES
2.2.1 Waste Acceptance, Storage, and Transportation (WAST)
Waste acceptance and transportation elements of the radioactive waste management system will accept SNF and HLW from commercial and government sites across the country and will transport the materials that will be stored in the repository. Information supporting this cost element is based upon data from the Analysis of the Total System Life Cycle Cost of the Civilian Radioactive Waste Management Program (TSLCC). Specifically, waste acceptance, storage, and transportation (WAST) estimates used the same logistic model and cost assumptions from the TSLCC to determine the costs for the 70,000 MTHM, Module 1, and Module 2 cases. The WAST estimates do not change between HTL, ITL, and LTL cases since the same quantities are shipped. For Module 2 estimates, data was adjusted upward from Module 1 estimates based upon data in the EIS engineering files which assumed additional waste packages and shipments for the GTCC and SPAR wastes.2.2.2 Nevada Transportation
Nevada railroad transportation costs include those engineering, construction, and operational costs, along with contingency, to support a branch rail line in Nevada to the repository. A specific route will be chosen at a later time and will be integrated with WAST activities. Information supporting this cost element is based upon data from the TSLCC.2.2.3 Program Integration
Program integration activities include systems engineering and integration, regulatory compliance, planning, international waste management and technology, and program control. Also included within this cost element are costs associated with regulatory and technical review board oversight, quality assurance (QA), human resources, and administration functions supporting DOE operations. The program integration costs only change between the 70,000 MTHM and Module 1 cases, and are not expected to change between the HTL, ITL, and LTL cases. Integration costs were based on the number of years of emplacement operations; information supporting this cost element is based upon data from the TSLCC.2.2.4 Institutional
Institutional costs cover those elements prescribed by the Nuclear Waste Policy Act (NWPA 1982) and do not directly impact the design, licensing, construction, operations, monitoring, and/or closure of the repository. Major cost elements that make up this cost element include payments equal to taxes, benefits, and other financial assistance. Institutional costs only change between the 70,000 MTHM and Module 1 cases, and are not expected to change between the HTL, ITL, and LTL cases. Institutional costs were also based on the number of years of emplacement operations and TSLCC data.3. MAJOR ASSUMPTIONS
The cost estimates for the EIS are based on a set of assumptions about the project from the VA reference case as modified to accommodate specific differences affecting design as noted in the respective engineering files. The following, however, present some of the major assumptions for the overall repository and this analysis.4. ESTIMATING METHODOLOGIES
The EIS costs estimates are rough estimates and follow generally accepted industry and DOE cost estimating guidelines. Factoring (or scaling) of costs was used based upon VA data. Where appropriate, adjustments were made upward depending upon the thermal loading case and any additional facility and emplacement tunnel requirements for each case. Estimating methodologies used in supporting the base case and this cost summary are as follows:5. COST SUMMARY
The total cost estimates were prepared for each EIS case as supported by the surface, subsurface, and engineered barrier/waste package engineering files. Below, Table 5-1a presents a single point estimate for each case for future costs from 1999 to 2116, and Table 5-1b presents the estimate from 2002 to 2116. Tables 5-2a, b, and c provide a breakdown of the cost by each element for Base Case, Module 1, and Module 2 cases. It should be noted that all costs presented are rounded off from calculated values and are in 1999 dollars.6. QUALITY
The EIS cost summaries were prepared following generally accepted industry and DOE cost estimating guidelines, and the summary report was prepared consistent with PRO-TS-003 Development of Technical Documents Not Subject to QARD Requirements, Rev. 1, effective December 21, 1998, as well as other guidance developed for the EIS. It should be noted that an evaluation "Environmental Impact Statement Support" (B00000000-01717-2200-00147 REV 01), dated February, 8, 1996, is on record and determined that these activities are not subject to the QARD.7. REFERENCES
7.1 DOCUMENTS CITED
CRWMS M&O 1997. Expanded Environmental Impact Statement Feasibility Assessment. B00000000-01717-5705-00074 REV 00, Las Vegas, Nevada: Author. ACC: MOL.19980427.0183. DOE 1998a. Viability Assessment of a Repository at Yucca Mountain, Volume. 5. DOE/RW-0508, December 1998. Washington, D.C.: U.S. Government Printing Office. ACC: MOL.19981007.0032. DOE 1998b. Analysis of the Total System Life Cycle Cost of the Civilian Radioactive Waste Management Program. DOE/RW-0510, December 1998. Washington, D.C.: U.S. Department of Energy, Office of Civilian Radioactive Waste Management. ACC: HQO.19980901.0001. DOE 1998c. Quality Assurance Requirements and Description. DOE/RW-0333P, REV 8, June 1998. Washington, D. C.: U.S. Department of Energy, Office of Civilian Radioactive Waste Management. ACC: MOL.19980601.0022. CRWMS M&O 1999a. Repository Surface Design Engineering Files Report. BCB000000-01717-5705-00009 REV 02, Las Vegas, Nevada: Author. ACC: MOL.19990310.0079. CRWMS M&O 1999b. Engineering File – Subsurface Repository. BCA000000-01717-5705-00005 REV 01, Las Vegas, Nevada: Author. ACC: MOL.19990310.0078. CRWMS M&O 1999c. Waste Package Final Update to EIS Engineering File. BBA000000-01717-5705-00019 REV 01, Las Vegas, Nevada: Author. ACC: MOL.19990330.0530.7.2 CODES, STANDARDS AND REGULATIONS
Nuclear Waste Policy Act of 1982. Public Law 97-425, 42 U.S.C. 10101-10226. 1983. TIC: 216801. Amendments to the Nuclear Waste Policy Act of 1982. Public Law 100-203, December 27, 1987, 100th Congress, Title V. TIC: 222510.
Previous Section | Next Section