Table 5-2a. Cost by Elements for 70,000 MTHM Case (in $Billions)a
|
70,000 MTHM |
|||
|
FY 1999 – FY 2116 |
HTL |
ITL |
LTL |
| MGR |
$ 20.2 |
$ 21.9 |
$ 24.1 |
| WAST |
$ 4.6 |
$ 4.6 |
$ 4.6 |
| NV Rail |
$ 0.8 |
$ 0.8 |
$ 0.8 |
| Program Integration |
$ 2.3 |
$ 2.3 |
$ 2.3 |
| Institutional |
$ 2.8 |
$ 2.8 |
$ 2.8 |
|
Total |
$ 30.7 |
$ 32.4 |
$ 34.6 |
|
FY 2002 – FY 2116 |
HTL |
ITL |
LTL |
| MGRb |
$ 19.3 |
$ 21.0 |
$ 23.2 |
| WAST |
$ 4.6 |
$ 4.6 |
$ 4.6 |
| NV Rail |
$ 0.8 |
$ 0.8 |
$ 0.8 |
| Program Integration |
$ 2.1 |
$ 2.1 |
$ 2.1 |
| Institutional |
$ 2.8 |
$ 2.8 |
$ 2.8 |
|
Total |
$ 29.5 |
$ 31.2 |
$ 33.4 |