Scientists on the Yucca Mountain Project used a tunnel boring machine,
to create an underground laboratory within Yucca Mountain, called
the Exploratory Studies Facility. The tests completed within
this facility have given scientists and engineers much-needed information
about the mountain s interior.
Impressive in size and capability, the tunnel boring machine and
all its trailing equipment weighs 860 tons and measures 140 meters
(460 feet) in length. It has 13 trailing decks, or work platforms,
that are towed behind the machine in the form of a train.
The 7.6-meter (25-foot)-diameter machine began its journey in September
1994 from a starter tunnel extending 60 meters (196 feet) into Yucca
Mountain.
To work properly, the machine was positioned inside a tunnel so
it could grip the sides of the tunnel and push the cutters into
the rock to advance the tunnel. Its hardy mechanical cutters chip
and grind their way through rock and soil. The cutter head, with
48 cutter discs 43 centimeters (17 inches) in diameter, chips and
flakes the rock. The chips (known as muck) move out through
the back of the machine on a series of conveyor belts to a designated
area outside the tunnel.
Tunnel boring was the most efficient and ultimately the most environmentally
sound and physically safe method for gaining access to the underground
environment found at Yucca Mountain. The machine consumed less money
and less time than drill-and-blast excavation, and performed with
minimal environmental disruption.
Tunnel boring machines are built to cope with varying underground
conditions. The same machine generally can adapt to both hard rock
and loose ground. Sometimes, the machine would encounter both conditions
in a single day. Often, the machine's operators did not know what
conditions they would face only a few meters ahead. The only thing
they could count on was that conditions would vary.
Tunnel boring machines also act as locomotives for cars carrying
special equipment or facilities. One of these cars provided a platform
for geologists taking rock samples. The same car carried cameras
that made detailed geological maps of the tunnels. These maps provided
a permanent record of the machine's underground passage and yielded
information about the geology of the area through which it passed.
This data is used by engineers to design the proposed repository.
By the spring of 1997, the Tunnel Boring Machine had advanced the
full course of the eight-kilometer (five-mile) tunnel and emerged
at the facility's south portal.
Maximizing the opportunity afforded by the tunnel and the entire
facility, scientists conducted studies to:
- Determine the rate of water seepage into the proposed repository
- Test the groundwater flow above and below the water table, including
how rain water and other fluids might move from the surface through
fractures and faults
- Determine how the distinct geologic units govern the flow of
gases and fluids within the mountain
- Establish, with thermal tests, the effects of waste-generated
heat upon the rock, water, and installed ground support systems
in a repository.
TBM facts and acronyms
Conveyor systems
- From the cutterhead to the rear of the TBM.
- From the rear of the TBM to the outside of the tunnel.
- From the outside of the tunnel to the muck pile.
Cutterhead
The rotating head at the front of the TBM that cuts the rock.
Cutterhead bearing
Two-row tapered roller. High capacity for hard rock.
Decks (also trailing decks)
Work platforms that are towed behind the TBM in the form of a train.
There are 13 decks on this TBM.
Design
Gripper Shield TBM, model 760, custom-built for Yucca Mountain.
Diameter
7.62 meters (25 feet).
ESF
Exploratory Studies Facility. An underground laboratory for scientists
to help determine if Yucca Mountain is suitable for the disposal
of high-level nuclear waste. The ESF is approximately a 10-kilometer
(6.2-mile) network of tunnels.
Forward shield
The metal parts of the TBM next to the rotary head that provide
temporary support and prevent rock material from falling and interfering
with the TBM cutting action.
Gantry
An elevated platform that moves with the TBM to all the roof of
the tunnel to be mapped.
Gripper shield
The mechanical protection that prevents individuals from access
to the grippers while they are engaged to the tunnel rib.
Gripper shoes
Large curved pressure plates that push against the rock wall, holding
the TBM steady, so that the cutterhead can push forward into the
rock.
Launch chamber
The initial 60 meters (196 feet) of the ESF where the TBM began
tunneling operations. This initial portion of the ESF was completed
using conventional drill-and-blast techniques.
Leak mitigation system
The devices installed on the TBM that minimize the spillage of fluids
used in the operation of the TBM, thereby reducing environmental
impacts.
Length
140 meters (460 feet).
Manufacturer
Construction & Tunneling Services, Inc. (CTS), Kent Washington.
It took approximately 10 months to manufacture the TBM.
Maximum advance rate
The maximum amount of distance the TBM will travel in a given amount
of time is 5.3 meters (18 feet) per hour.
Minimum turn radius
The measure of how tight a turn the TBM can make. The TBM’s
minimum turn radius is 151 meters (500 feet).
Muck
The earth and rock that are excavated during TBM operation.
North Portal
North opening to the ESF. The ESF also has a South Portal.
Operating voltage
12.47 KV.
Operations
Team of companies contracted to the Department of Energy, including
Kiewit/Parsons Brinckerhoff, Fluor Daniel, Morrison-Knudsen, and
Duke Engineering Services. Kiewit/Parsons Brinckerhoff was the company
contracted to operate the TBM.
Pad
The areas near the portal entrances, that accommodated all the facilities
used to construct the ESF. Both North Portal and South Portal pads
were constructed.
Power
12 electric motors generating 3,800 horsepower.
Tail shield
The portion of the tunnel boring machine located behind the cutterhead
that protects the TBM crew from falling rocks when installing ground
support. This overhead section is constructed of two-inch-thick
steel and is 12 feet long.
Weight
720 tons (1,440,000) lbs.).
Note: From March through October 1998, miners used a smaller, 5-meter-
(16.5-foot) diameter tunnel boring machine to excavate a tunnel
called the Enhanced Characterization of the Repository Block (ECRB).
This 2.7-kilometer (1.7-mile) ECRB tunnel, or cross drift extends
from the north portion of the Exploratory Studies Facility and crosses
above the actual area being studied for a repository.
Scientists will collect data on geology and the behavior of water
within that area to verify models and predictions about performance
of the natural features of Yucca Mountain.
|