C-CA-CAM Building Complex Demolition and Site Restoration
CX(s) Applied: B1.11, B1.16, B1.17, B1.23, B1.24, B1.27, B1.30, B1.33, B1.34
Date: 01/09/2013
Location(s): Pennsylvania
Offices(s): Naval Nuclear Propulsion Program
Existing Regulations
B1.16: Asbestos removal
Removal of asbestos-containing materials from buildings in accordance with applicable requirements (such as 40 CFR part 61, “National Emission Standards for Hazardous Air Pollutants”; 40 CFR part 763, “Asbestos”; 29 CFR part 1910, subpart I, “Personal Protective Equipment”; and 29 CFR part 1926, “Safety and Health Regulations for Construction”; and appropriate state and local requirements, including certification of removal contractors and technicians).
Previous Regulations
Categorical Exclusion Determinations dated before November 14th, 2011 were issued under previous DOE NEPA regulations. See the Notice of Final Rulemaking (76 FR 63763, 10/13/2011) for information changes to this categorical exclusion.
DOCUMENTS AVAILABLE FOR DOWNLOAD
-
January 9, 2013
-
December 14, 2012
Washington River Protection Solutions LLC - Asbestos Removal
CX(s) Applied: B1.16
Date: 12/14/2012
Location(s): Washington
Offices(s): River Protection-Richland Operations Office -
December 5, 2012
Mission Support Alliance Annual Categorical Exclusion for Asbestos Removal under 10 CFR 1021, Subpart D, Appendix B
CX(s) Applied: B1.16
Date: 12/05/2012
Location(s): Washington
Offices(s): River Protection-Richland Operations Office -
November 19, 2012
Asbestos Abatement Actions
CX(s) Applied: B1.16
Date: 11/19/2012
Location(s): Tennessee, California, California, Virginia
Offices(s): Oak Ridge Office -
November 19, 2012
Ventilation Activities
CX(s) Applied: B1.4, B1.16, B2.1, B2.3
Date: 11/19/2012
Location(s): Tennessee, California, California, Virginia
Offices(s): Oak Ridge Office -
September 21, 2012
Routine and Non-Routine Activities at the Grand Junction, Colorado, Office Site
CX(s) Applied: B1.3, B1.4, B1.7, B1.13, B1.15, B1.16, B1.23, B1.24, B1.28, B2.1, B2.2, B2.4, B2.5, B3.1, B5.16, B6.1
Date: 09/21/2012
Location(s): Grand Junction
Offices(s): Legacy Management -
August 3, 2012
CH2MHill Plateau Remediation Company - Asbestos Removal Actions
CX(s) Applied: B1.16
Date: 08/03/2012
Location(s): Washington
Offices(s): River Protection-Richland Operations Office -
July 16, 2012
Routine Maintenance
CX(s) Applied: B1.3, B1.4, B1.8, B1.16, B1.17
Date: 07/16/2012
Location(s): Washington
Offices(s): Pacific Northwest Site Office -
July 16, 2012
Building 1 Renovation
CX(s) Applied: B1.15, B1.16, B2.1, B2.2, B2.5
Date: 07/16/2012
Location(s): West Virginia
Offices(s): National Energy Technology Laboratory -
June 8, 2012
Renovations and Maintenance Activities for Buildings, Structures, Infrastructures and Equipment
CX(s) Applied: B1.3, 61.4, 61.5, B1.11, B1.15, B1.16, B1.17, 81.22, B1.27, 62.1, B2.2, B2.3, 62.5
Date: 06/08/2012
Location(s): Illinois
Offices(s): New Brunswick Laboratory -
April 20, 2012
Prototype Staff Building 114
CX(s) Applied: B1.15, B1.16, B1.23
Date: 04/20/2012
Location(s): New York
Offices(s): Naval Nuclear Propulsion Program -
April 20, 2012
Security Upgrades Major Construction Project
CX(s) Applied: B1.11, B1.15, B1.16, B1.23, B2.2
Date: 04/20/2012
Location(s): New York
Offices(s): Naval Nuclear Propulsion Program -
April 19, 2012
L-Building Demolition and Site Restoration
CX(s) Applied: B1.16, B1.17, B1.23
Date: 04/19/2020
Location(s): Pennsylvania
Offices(s): Naval Nuclear Propulsion Program -
January 13, 2012
Washington River Protection Solutions LLC - Proposed Actions For Calendar Year 2012
CX(s) Applied: B1.16
Date: 01/13/2012
Location(s): Washington
Offices(s): River Protection-Richland Operations Office -
November 22, 2011
Electrical District 2 - Saguaro No. 1 Pole Replacement
CX(s) Applied: B1.3, B1.16, B1.19, B1.23
Date: 11/22/2011
Location(s): Arizona
Offices(s): Western Area Power Administration-Desert Southwest Region -
October 17, 2011
Black Point Communication Site Building Replacement
CX(s) Applied: B1.3, B1.16, B1.19, B1.23
Date: 10/17/2011
Location(s): California
Offices(s): Western Area Power Administration-Desert Southwest Region -
September 28, 2011
Building 903 Renovation
CX(s) Applied: B1.16, B1.29, B2.1, B2.2, B2.5
Date: 09/28/2011
Location(s): Pittsburgh, Pennsylvania
Office(s): Fossil Energy, National Energy Technology Laboratory -
September 6, 2011
Building 840 Office Relocation, Heat Treating Equipment Removal, and Fire Protection Upgrades
CX(s) Applied: B1.3, B1.16, B2.1
Date: 09/06/2011
Location(s): Albuquerque, New Mexico
Office(s): NNSA-Headquarters, Golden Field Office -
August 3, 2011
B-Press and Extruder Modification
CX(s) Applied: A7, B1.3, B1.15, B1.16, B1.27, B1.31
Date: 08/03/2011
Location(s): Amarillo, Texas
Office(s): Pantex Site Office -
August 1, 2011
Building 20 Fleet Interactive Display Equipment Facility Expansion
CX(s) Applied: B1.15, B1.16, B2.2, B2.5
Date: 08/01/2011
Location(s): New York
Offices(s): Naval Nuclear Propulsion Program -
June 20, 2011
Removal of Asbestos from Buildings
CX(s) Applied: B1.16
Date: 06/20/2011
Location(s): Richland, Washington
Office(s): Office of River Protection-Richland Office -
April 12, 2011
Building 7 Roof Replacement Project
CX(s) Applied: B1.3, B1.16
Date: 04/12/2011
Location(s): Morgantown, West Virginia
Office(s): Fossil Energy, National Energy Technology Laboratory -
April 12, 2011
Connecticut-City-Hamden, Town of
CX(s) Applied: A1, A9, A11, B1.16, B1.32, B2.5, B5.1, B6.1
Date: 04/12/2011
Location(s): Hamden, Connecticut
Office(s): Energy Efficiency and Renewable Energy -
April 8, 2011
Field Test Laboratory Building 158-03 Install Condensing Unit
CX(s) Applied: B1.4, B1.16
Date: 04/08/2011
Location(s): Golden, Colorado
Office(s): Energy Efficiency and Renewable Energy, Golden Field Office -
January 5, 2011
Asbestos Involved Work in K-Area Complex Facilities
CX(s) Applied: B1.16
Date: 01/05/2011
Location(s): Aiken, South Carolina
Office(s): Savannah River Operations Office