You are here

EA-1611: Final Environmental Assessment

Interconnection Request for the Colorado Highlands Wind Project

This Environmental Assessment (EA) was prepared in accordance with NEPA to assess the impacts of constructing and operating the wind Project, which would be enabled by Western’s execution of the interconnect agreement (a Federal action). The proposed Project would include sixty (60) General Electric (GE) 1.5 megawatt (MW) SLE wind turbines with a total Project output nameplate capacity of ninety (90) MW of renewable energy.